Ambrosia begins work on Texas battery factory for off-grid data centers
The company is bringing battery-pack production in-house to support solar-powered sites. Its first commercial plant targets 30 megawatts of continuous power and 99.3% uptime.
Listen to this story
The audio brief
Story brief
3 key pointsAmbrosia’s factory is meant to turn its solar-plus-storage power-plant design into a repeatable supply chain for off-grid data centers, not to sell batteries as a standalone product. The 10 GWh facility will assemble packs from purchased cells and is expected to reach full production in two to three years; output is forecast to support about 300 MW of new power-plant capacity annually, not capacity already serving customers. Its economics and reliability remain company claims awaiting commercial-scale proof.
- 01
Ambrosia’s planned West Texas plant pairs 300 MW of solar and 660 MWh of storage to target 30 MW of continuous power and 99.3% uptime.
- 02
CEO Ben Longmier puts pack costs at about 1.3 times bare-cell costs, versus five to seven times for typical stationary systems; the comparison is unverified.
- 03
Longmier says the pilot can deliver 200 kW continuously and that sections have operated for more than 100 days.
Ambrosia Energy is building the battery supply for data centers designed to run on solar power without the grid. Work has begun on a planned 10 gigawatt-hour battery factory near Austin, Texas, CEO Ben Longmier said at TechCrunch Disrupt. The company expects the facility to reach full production in two to three years.
The 150,000-square-foot factory would supply Ambrosia’s own power-plant projects. Longmier told the San Francisco conference that its output would let the company build about 300 megawatts of power-plant capacity per year at its field sites. That is a deployment forecast, not power already available to data-center customers.
Ambrosia emerged from stealth in June with a plan to build data-center power plants at $100 per megawatt-hour. Longmier and co-founder Sara Spangelo chose solar panels paired with batteries as what they judged the cheapest option and the fastest to deploy.
Build the packs, buy the cells
The manufacturing strategy does not require Ambrosia to make the battery cells themselves. It buys existing cells and assembles them into its own packs. Longmier said the company has simplified both battery packs and solar mounts, cutting part counts and making many components in a factory rather than buying finished components from outside suppliers.
He put Ambrosia’s battery-pack cost at about 1.3 times the cost of the bare cells, compared with five to seven times for most stationary storage systems. He also claimed its pack has roughly 100 times fewer parts than competing designs the company has seen. Those comparisons are Ambrosia’s figures, not independently verified results.
That cost argument extends beyond the factory. Longmier said Ambrosia can profitably sell electricity at $100 per megawatt-hour even after installing extra solar panels and batteries to support continuous operation. He described that price as competitive with natural-gas turbines that large data-center operators are planning to use.
Ambrosia plans this amount of solar-panel capacity at its first commercial plant.
The planned batteries would store electricity for use beyond daylight hours.
The combined installation is designed to deliver this continuous output, according to Longmier.
From daylight generation to overnight supply
Ambrosia plans to begin work on its first commercial power plant in West Texas later in 2026, Longmier said. That project is the intended commercial application of the solar-and-battery approach behind the factory: a power supply built to keep a data center operating beyond the hours when panels generate electricity.
During the day, solar panels would serve the data center while charging the batteries. The batteries would then discharge at night and on cloudy days. The proposed plant therefore pairs a much larger solar installation with a smaller continuous power commitment, rather than promising its full solar-panel capacity around the clock.
The West Texas design targets 99.3% uptime. That is a company goal for the planned commercial facility, not an operating record. It also puts a qualification beside the promise of continuous power: the design is intended to supply electricity day and night, but its stated uptime target is below 100%.
Ambrosia has tested the approach at a smaller scale. Longmier said sections of its pilot power plant have operated continuously for more than 100 days, and that the pilot can generate 200 kilowatts around the clock. The commercial project would move from that pilot-scale output to a 30-megawatt continuous-power target.