Native planting and creek restoration have won local praise. Critics say those benefits cannot answer the pollution and resource demands of AI infrastructure.
Loading page…
Native planting and creek restoration have won local praise. Critics say those benefits cannot answer the pollution and resource demands of AI infrastructure.
Listen to this story
Microsoft’s September plan expands nature-focused restoration from a Netherlands project begun in 2022 to more than 20 data-center sites in the US and Germany, with the approach planned for every new US project. Site-specific work may include native buffers, pollinator habitat and ecosystem repairs, but some features remain under consideration rather than committed at every location. The initiative can deliver local ecological benefits, yet advocates question whether landscaping can address the pollution and resource demands associated with powering data centers.
In Mount Pleasant, Wisconsin, Microsoft funded a $4.2 million creek-restoration project in 2023 at property being repurposed from the shuttered Foxconn factory.
In San Antonio, Microsoft cut down more than 2,600 trees across 33 acres in 2022 and says it is investing in restoration across more than 400 acres.
Public Citizen’s Texas director argues that habitat restoration cannot compensate for pollution from gas plants built to power data centers.
Microsoft is promising to restore ecosystems around more than 20 data-center sites in the US and Germany, and apply the approach to all new US projects. The plan has earned praise for concrete local improvements. But advocates quoted in The Verge’s October 2 article question whether greener grounds can meaningfully address the pollution and resource demands behind AI infrastructure.
Microsoft calls the approach biomimicry: taking inspiration from nature. Here, that means blending facilities into their surroundings through native trees, gardens and repairs to damaged ecosystems. The company began such work at a Netherlands data center in 2022. Its September announcement extends the approach across the US and Germany, with a growing number of projects elsewhere.
The designs will vary by location rather than follow one landscaping template. Kaitlin Chuzi, Microsoft’s director of global land strategy, told The Verge the company wants to enhance existing habitat and restore what has been lost. Some measures remain under consideration, rather than confirmed features at every site:
In Mount Pleasant, Wisconsin, Microsoft funded a $4.2 million creek-restoration project in 2023 on property being repurposed from the shuttered Foxconn LCD factory. It worked with the Root-Pike Watershed Initiative Network to restore the creek’s flow.
The group’s executive director, Dave Giordano, also praised Microsoft for adding forebays to stormwater ponds. These compartments help keep sediment from escaping. He described the measure as unusual locally.
San Antonio presents a harder backdrop. Microsoft cut down more than 2,600 trees across 33 acres for a data center in 2022. Microsoft spokesperson Jennifer Lyons told The Verge the company is now investing in more than 400 acres of woodland and pollinator prairie restoration there.
I cannot really see any level of biomimicry investment that makes a gas plant a desirable neighbor.
Adrian Shelley, Texas director of Public Citizen, speaking to The Verge
Shelley supports nature-based solutions suited to native ecosystems. His objection is their reach: he argues they cannot compensate for pollution from gas plants built to power data centers. Microsoft’s carbon pollution rose 25 percent in 2025, according to its latest sustainability report, cited by The Verge.
Houston Advanced Research Center scientist Erin Kinney is optimistic about tailoring restoration to each location. For her, the test is how Microsoft measures the benefits and shares those results with residents. A project must fit community expectations as well as the local ecology.
Loading discussion...
Join the conversation
Explain how much local ecological benefits should weigh against broader environmental costs.
Be the first to share a perspective or an experience.
Reader comments
Newest comments first. Replies stay oldest first.