North Dakota Hearing Puts AI Data-Center Permits and NDAs Under Local Scrutiny
Public frustration over project timing is now running alongside two distinct policy questions: whether to pause new hyperscale permits and whether to restrict nondisclosure agreements.
Listen to this story
The audio brief
Story brief
3 key pointsNorth Dakota’s AI and Data Center Committee heard objections to the speed and transparency of proposed hyperscale projects, but reached no decision on permits or confidentiality rules. Residents advocated a temporary pause on new large-scale data-center permits, while county officials defended local siting authority and called for clearer boundaries around nondisclosure agreements. Lawmakers are separately scheduled...
- 01
A farmer said residents learned about an Oliver County project less than three months before construction began.
- 02
The North Dakota Association of Counties said counties determine where and under what conditions data centers are built.
- 03
Vern Thompson urged lawmakers to pause new hyperscale data-center permits, citing his assertion that most residents support a temporary halt.
North Dakota lawmakers heard public and industry views on AI and data centers as residents challenged the pace of proposed development and the handling of the hearing. Legislators are also scheduled to consider a temporary ban on nondisclosure agreements for data centers and other industrial developments later this week.
The Artificial Intelligence and Data Center Committee was announced in June. It has previously examined AI regulation, AI in education, risks to youth and data-center concerns; multiple data-center projects have been proposed in the state.
A hearing over pace and participation
Some attendees objected to special-interest groups speaking before the public, and committee Chairman Jonathan Warrey warned that disruptions could lead to removal by the Highway Patrol. Community members also said projects felt rushed. Michel Berg, a local farmer, said the public learned of an Oliver County project less than three months before construction began.
The confidentiality question remains separate
The planned NDA discussion is a separate legislative item from Thompson’s request for a permit pause. Aaron Birst, executive director of the North Dakota Association of Counties, said another law may not be needed, but lawmakers may need to clarify what is and is not covered by an NDA.
The committee’s agenda reaches beyond permits
- Presentations include policy experts, the energy industry, and state utility and pollution regulators.
- Public comment was scheduled for 11:15 a.m. during Monday’s meeting at the state Capitol.
The hearing did not produce a settled policy on hyperscale permits or NDAs. It did make the divide clear: some participants want a halt on new large projects, while county officials emphasized local siting authority and clearer rules around confidentiality agreements.
Sources
- kfyrtv.comPublic voices concerns over AI, data center discussions
- kfgo.comPublic can testify Monday at AI and data center committee