Data Center Watch Counts 45 U.S. Projects Delayed or Blocked by Opposition

The second-quarter tally shows local consent becoming a practical constraint on AI infrastructure, alongside battles over water, electricity and where new facilities may be built.

By 3 min read
Data Center Watch Counts 45 U.S. Projects Delayed or Blocked by Opposition
Data Center Watch Counts 45 U.S. Projects Delayed or Blocked by Opposition

Listen to this story

The audio brief

About 1:28
0:001:28
Read transcript
Forty-five large U.S. data-center projects, representing sixty-eight billion dollars, were delayed or blocked by opposition between April and June 2026, according to Data Center Watch. The affected developments made up more than half of the new large-scale projects the group tracked in the second quarter. That does not mean the sixty-eight billion dollars is permanently lost: some projects could still move forward after delays or changes. But the tally shows that local consent is becoming a practical constraint on the infrastructure needed to run AI systems. The resistance is also moving earlier in the process. Communities are pursuing moratoriums that can halt new construction before a developer even files for permits. And roughly thirty statehouses introduced or adopted rules covering data-center siting, electricity, or water. Data Center Watch, a project of AI intelligence company 10a Labs, counted 843 opposition groups across 49 states, excluding Hawaii. In Tennessee, one petition against a project passed 500,000 signatures on Change.org. Opposition was lower than in the first quarter, when 75 projects worth about 130 billion dollars were affected. Still, the issue remained central to the development pipeline. And for the first time, the group documented protests in Europe, Australia, and South Africa. The constraint to watch is what happens before construction begins: whether local and state decisions can keep pace with demand for new computing capacity.

Story brief

3 key points

Data Center Watch’s Q2 2026 tally points to permitting and political friction as a growing constraint on AI infrastructure expansion: 45 U.S. projects representing $68 billion were delayed or blocked, while moratoriums and state rules can intervene before formal permit filings. The figure is not a loss forecast—projects may eventually proceed—and it declined from Q1. Still, opposition spans 843 groups across 49...

  1. 01

    45 projects worth $68 billion were affected from April through June; delays and blocks do not mean the investment is permanently lost.

  2. 02

    Moratoriums can stop projects before permitting; roughly 30 statehouses introduced or adopted data-center siting, electricity, or water rules.

  3. 03

    Data Center Watch counted 843 opposition groups across 49 states; a Tennessee petition exceeded 500,000 signatures.

More than half of the new large-scale U.S. data-center developments tracked in the second quarter faced disruption from local opposition. Data Center Watch counted 45 projects, valued at $68 billion, that were blocked or delayed between April and June.

The finding turns a diffuse backlash into a measure of construction risk for the facilities needed to run AI systems. It is a count of projects affected by opposition, not a forecast that all of their investment will disappear: a delay or block can take different forms and project counts fluctuate from quarter to quarter.

Opposition is moving into permits and policy

The reported disputes are not confined to individual planning fights. Data Center Watch said communities are pursuing moratoriums on new construction, sometimes before developers can submit permit applications. It also counted roughly 30 statehouses that introduced or adopted rules touching data-center siting, electricity or water.

A national pattern with local pressure points

Data Center Watch, a project of AI intelligence company 10a Labs, identified 843 opposition groups across 49 states, excluding Hawaii. Its tally captures campaigns around specific facilities as well as broader moves to shape where data centers can be placed and what resource rules they face.

The report points to three ways resistance is gaining force

  • Local moratoriums can halt or postpone new construction before a developer’s permit process begins.
  • State-level rules are addressing the siting of facilities and their demands on electricity and water.
  • Online organizing can scale quickly: a Tennessee petition against one project drew more than 500,000 Change.org signatures during the quarter.

The second-quarter total was lower than the 75 U.S. projects worth roughly $130 billion that Data Center Watch said faced opposition in the first quarter. But the later total still covered more than half of newly tracked large developments, suggesting the issue remains central to the pipeline rather than limited to a few exceptional proposals.

The backlash is no longer only American

For the first time in its two-year research history, the group also documented data-center protests outside the United States, including in Europe, Australia and South Africa. Those campaigns similarly focus on particular projects, planning approvals and resource use, according to the report.

That makes the immediate question less about whether AI developers want additional computing capacity and more about what happens before construction begins. Local governments are increasingly being asked to decide whether a proposed facility’s conditions, benefits and resource demands justify letting it proceed.

Sources

  1. bloomberg.comAI backlash puts $68 billion in U.S. data center projects on hold