Illinois’ electricity planners have put data-center growth at the center of the state’s power-supply challenge. The Illinois Commerce Commission’s initial integrated resource plan report, issued November 16, 2026, identifies that growth as the primary pressure on adequate electricity resources, while finding that a diverse resource mix can deliver a reliable clean power system.
An integrated resource plan is a roadmap for meeting forecast electricity demand. This assessment examines several possible energy futures rather than selecting one construction program. The commission also places Illinois’ supply challenge in a regional and national context: the state’s electricity system does not operate in isolation, and data-center demand is driving pressure beyond its borders.
Comparing possible power systems
The modeling explores how different combinations of electricity resources could affect reliability, affordability and the state’s clean-energy and emissions standards. It also examines equity and other consumer impacts. Those are separate dimensions of the assessment: the planning task includes both whether a system can serve demand and how its choices affect Illinois electricity customers.
The report varies more than the mix of resources supplying electricity. Its scenarios also explore transmission expansion, power-plant retirements and emerging energy technologies. These choices are examined together as potential energy futures, allowing the agencies to assess uncertainty rather than treat a single set of assumptions as the only possible outcome.
The commission’s stated approach is to evaluate available options and balance affordability, reliability and emissions reductions. Its finding that clean power can remain reliable rests on using a diverse pool of resources, rather than presenting one resource as the answer to rising demand.
The report is not a prescriptive fix for Illinois’ rising energy demands.
Illinois Commerce Commission
Demand forecasts and customer costs
The assessment follows a stakeholder process that exposed parts of the modeling to review before publication. A July 31 workshop covered the final electricity-demand forecasts used in the analysis, alongside the methodology for evaluating how different resources contribute to meeting reliability needs. A September 24 workshop reviewed draft modeling results and invited stakeholder feedback.
Customer costs were also a dedicated topic. A May 26 workshop focused on the methodology for assessing customer cost impacts in the modeling. The published report’s supporting materials include analyses of costs and energy burden, emissions and equity, transmission assumptions, and the balance between electricity demand and resources.
Recommendations come next
The work is required by Illinois’ Clean and Reliable Grid Affordability Act. Commission staff coordinate the effort with the Illinois Power Agency, Illinois Finance Authority and Illinois Environmental Protection Agency. Their mandate includes safe, adequate and reliable electricity service, environmental sustainability and the lowest cost over time, consistent with state energy-policy goals.
Publication begins the commission’s first integrated resource plan review; it does not complete it. The report offers high-level considerations for the approval proceeding. Commission staff and the other participating state agencies are expected to file specific recommendations during that process, moving from the assessment’s possible futures toward proposals for commission consideration.
The next formal endpoint is an implementation decision, expected by November 2027. That decision will come through a final order from the commission’s five appointed commissioners.