US data-center developers propose more than 100 gas plants, MIT Technology Review finds
Connection approvals can take as long as a decade. Building outside the grid offers a workaround, but could worsen emissions and raise other customers’ bills.
Loading page…
Connection approvals can take as long as a decade. Building outside the grid offers a workaround, but could worsen emissions and raise other customers’ bills.
Listen to this story
MIT Technology Review counted more than 100 natural-gas power plants proposed by US data-center developers as of October 2026, reflecting efforts to secure electricity without waiting for grid interconnection. The count is a pipeline of announced projects—not operating plants or a measure of planned generation capacity. One example is Net Power’s Texas project, designed to supply an adjacent data center without connecting to ERCOT; dedicated gas generation could affect emissions and other customers’ energy bills, though those impacts have not been measured for this pipeline.
Grid-connection waits can reach a decade, although the article notes that duration is not typical for every project.
Net Power described its Texas project in a November 12 quarterly filing; the planned plant would serve a neighboring data center directly.
MIT Technology Review warns that the gas-power push could shape the grid and climate for decades.
US data-center developers had announced plans for more than 100 natural-gas power plants by October 2026, MIT Technology Review reported on November 24. The tally puts a number on the push to supply the AI buildout with dedicated generation, as some developers choose their own power plants over waiting for access to the electricity grid.
Getting approval to connect to the electricity grid is one of the biggest obstacles to building a data center. The wait can last as long as a decade, though that is not a typical duration established for every project. Some developers are responding by building off-grid gas plants that supply their facilities directly, avoiding the grid-connection approval process.
A Texas project illustrates the approach. In its November 12 quarterly filing, Net Power said it was developing a natural-gas power project to serve a data center located alongside it. The planned supply would operate without connecting to the ERCOT grid, rather than depend on a grid connection to deliver electricity to the facility.
MIT Technology Review warns that bypassing the grid with gas plants could worsen climate emissions and potentially raise energy bills for other customers. Those possible costs reach beyond the developers securing their own electricity. The bill warning concerns people outside the projects; it is a potential consequence, not a measured increase attributed to this national pipeline of plants.
The time horizon also extends beyond today’s construction bottleneck. MIT Technology Review warns that the push for gas power could shape both the electricity grid and the climate for decades.
Loading discussion...
Join the conversation
Explain how you would weigh faster development against potential public costs.
Be the first to share a perspective or an experience.
Reader comments
Newest comments first. Replies stay oldest first.